Rooftop Solar Rules: Why the Centre Wants Batteries and Charges for Excess Power
Why in news?
Recently, the Union Power Ministry proposed amendments to the Electricity (Rights of Consumers) Rules, 2020, reshaping how rooftop solar consumers use and feed electricity into the grid.
The changes come as India's power grid struggles to integrate a rapidly growing share of renewable energy, with the proposed rules allowing states to mandate battery storage and levy charges on certain consumers for surplus solar power fed into the grid.
What’s in Today’s Article?
- What's Driving This Policy Shift?
- The Core Problem: Net Metering and DISCOM Finances
- Key Proposed Changes
What's Driving This Policy Shift?
- India's distributed solar capacity currently stands at 33.41 gigawatts (GW).
- Under the PM Surya Ghar: Muft Bijli Yojana, more than 13,000 rooftop solar installations are being added daily, with around 65 lakh households having adopted rooftop solar as of November 2026.
- However, this rapid growth creates challenges:
- Grid management complications from large volumes of decentralised surplus power fed in during the day.
- Financial strain on DISCOMs (distribution companies), which already have weak balance sheets.
The Core Problem: Net Metering and DISCOM Finances
- Most grid-connected rooftop solar systems operate under net metering, which lets consumers offset grid-drawn electricity against surplus solar power fed back, paying only for net consumption.
- The government argues this mechanism hurts DISCOM finances by preventing full recovery of fixed costs.
- DISCOM fixed costs include: capacity payments to thermal generators, transmission costs, employee salaries, and infrastructure maintenance — all payable regardless of energy sales.
- The billing distortion: Since electricity tariffs typically rise with higher consumption (slab-based pricing), a household with high total usage can show low net usage under net metering — placing it in a cheaper tariff slab.
- This means such consumers pay less per unit than their actual consumption justifies. Other consumers end up subsidising the difference.
Key Proposed Changes
- Charges for Excess Power Injection
- State electricity regulators can set a net metering limit (threshold).
- Systems exceeding this threshold could be charged:
- For the imputed cost of storage — since the grid effectively functions as a "battery" holding excess daytime power for later use.
- For network losses.
- No charges can be levied up to the regulator-set threshold; beyond it, charges depend on state-specific conditions.
- Battery Storage Mandate
- Consumers can install rooftop solar capacity higher than their sanctioned load, subject to state regulator limits.
- However, electricity can be injected into the grid only up to the sanctioned load, unless the distribution utility authorises otherwise.
- Unauthorised excess injection will not be eligible for payment/compensation and may attract penalties specified by the State Electricity Regulatory Commission (SERC).
- State regulators are empowered to determine:
- The capacity threshold beyond which rooftop solar installations must have an Energy Storage System (ESS).
- The corresponding storage capacity requirement — set as a proportion of daily generation, or 20% by default.
- Default Applicability: Unless specified otherwise, this mandate applies to installations above 10 kilowatts (kW) — notably higher than the typical 3-5 kW installed by most Indian households.
- Implementation Timeline: Proposed from April 1, 2028, giving stakeholders time for regulatory and investment preparation.
- Rationale: With battery storage costs declining, integrating ESS with rooftop solar has become economically viable, ensuring reliable power during non-solar hours and greater energy independence for commercial/industrial users.
- Time-of-Day (ToD) Tariff Extension
- ToD tariff is a pricing model where per-unit electricity rates vary based on the time of consumption, rather than staying flat.
- Implementation deadlines have been extended, aligned with the smart-meter rollout:
- April 1, 2028 for consumers above 10 kW (previously April 1, 2024).
- April 1, 2029 for other consumers, excluding agricultural users (previously April 1, 2025).
- States can also set their own solar and peak hours based on local conditions, instead of following a fixed 8-hour solar window.
- Billing Error Resolution
- To address inflated or unusually low bills from billing errors, distribution licensees must review and resolve cases within 30 days if billed consumption is:
- More than 5 times, or
- Less than one-fifth of the consumer's average consumption over the previous six billing cycles.
- State regulators may revise these thresholds based on local consumption patterns.
- To address inflated or unusually low bills from billing errors, distribution licensees must review and resolve cases within 30 days if billed consumption is:
Why This Matters?
- These changes attempt to balance two competing goals: encouraging rooftop solar adoption (central to India's renewable energy targets) while protecting DISCOMs' financial viability and overall grid stability.
- Incentives are also proposed to shift consumer electricity usage to periods of surplus supply or lower demand, improving grid efficiency.
Conclusion
The proposed rules reflect a necessary recalibration as India's rooftop solar revolution matures — shifting from pure incentivisation to a more sustainable framework that accounts for grid costs and DISCOM viability.
Striking the right balance between consumer affordability and distribution company solvency will be crucial to sustaining India's renewable energy momentum without destabilising the broader power sector.